SolarTech Study Reports Massive Procedural Delays for Customers – PV Group

‘San Jose, CA – Wednesday, January 27, 2010: SolarTech (www.solartech.org), an initiative of the Silicon Valley Leadership Group, released a white paper, “Addressing Institutional Barriers, Opportunities for Streamlining Project Timelines” that finds for every typical 4-5kW residential system, the average 5 day on-site installation masks an average of 100-120 days in procedural work. The paper identifies challenges within today’s solar project development cycle and suggests methods to reduce project cycle times, while creating uniform, efficient and repeatable processes, resulting in better customer service and lower administrative costs of delivering solar energy solutions.’

via PV Group – SolarTech Study Reports Massive Procedural Delays for Customers.